You submitted the RFI ten days ago. The concrete pour is scheduled for Thursday. Nobody has responded, and you're not sure whether to call, re-send, or just make the call yourself and document it later.
That's not a workload problem on the architect's end— it's usually a format problem on yours. A Navigant Construction Forum study1 of more than one million RFIs found that approximately 22% of all RFIs on commercial construction projects never receive a formal response. The same research identified unanswered RFIs as one of the strongest leading indicators of disputes arising later in the project.
This guide is for the person writing and submitting the RFI, not the design team receiving it. If you're on the responder side, the guide to responding to RFIs in construction covers that workflow. The rfi format in construction itself— specifically two or three fields most contractors leave vague— is where response time is made or lost. This guide shows you which ones.
The 8 Required Fields in an RFI Format for Construction
A construction RFI format requires eight fields: project identification, RFI number, submission date with response deadline, requester information, a single clear question, specific drawing and specification references, supporting documentation, and a proposed solution.
AIA Document G716-2004— the American Institute of Architects' standard RFI form— establishes the baseline template that Procore, Autodesk Construction Cloud, and most commercial platforms replicate2. (Note: AIA issued an updated form, F706-2024— check your contract documents for which version governs your project.) Most delays trace back to three of these eight fields: the question, the drawing reference, and the proposed solution.
Here's what each field requires:
| Field | What Goes In It | Good Example |
|---|---|---|
| Project Name & Number | Full project name, contract number | "Harbor View Office Complex— Contract No. 2024-GC-041" |
| RFI Number | Sequential log number, unique per project | "RFI-0047" |
| Date Submitted / Response Deadline | Submit date + date you need an answer | Submitted: Oct 6, 2026; Response needed: Oct 13, 2026 |
| Requester | Name, company, phone and email | "James Ortega, Summit General Contractors, [email protected]" |
| Subject / Issue Description | One clear question; the specific ambiguity | "Rebar lap splice length conflict between structural drawings and specifications" |
| Drawing & Spec References | Exact sheet, detail, and gridline; spec section and page | "See Drawing S-3.1, Detail 4, Grid C-4; Spec Section 03 20 00, Page 12" |
| Supporting Documentation | Photos, markups, relevant field conditions | Attach marked-up drawing showing the conflict |
| Proposed Solution | Your recommended resolution, framed as a suggestion | "We propose using 36-bar-diameter per the spec. Awaiting your confirmation." |
One clarification worth stating plainly: an RFI response does not authorize work that would increase project cost or time— that requires a separate change order. AIA G716 is explicit on this2, and knowing it prevents contractors from treating an RFI response as broader authorization than it actually is.
Every field exists because the reviewer needs it to act. Most contractors fill in all eight. The three that actually determine whether you get an answer are the question, the drawing reference, and the proposed solution.
What a Good RFI Looks Like Compared to a Bad One
A bad RFI forces the reviewer to do investigative work before they can even answer. A good RFI gives the reviewer everything they need to respond in a single review.
Here's the same rebar conflict written two ways:
| Element | Bad RFI | Good RFI |
|---|---|---|
| Subject | "Rebar question" | "Lap splice conflict— Drawing S-3.1 vs. Spec 03 20 00" |
| Question | "There's a conflict in the drawings. What do we do?" | "Drawing S-3.1, Detail 4, Grid C-4 specifies 24-bar-diameter lap splice. Spec Section 03 20 00, Page 12 specifies 36-bar-diameter. Which governs?" |
| Drawing reference | None | "See attached markup of Drawing S-3.1, Detail 4" |
| Proposed solution | None | "We propose 36-bar-diameter per the spec. Please confirm." |
| Deadline | None | "Response needed by Oct 13— concrete pour scheduled Oct 17" |
| Supporting docs | None | Marked-up drawing attached |
Both describe the same field issue. One requires the reviewer to call you back before they can even read the question. The other takes ten minutes to answer.
Young Architect puts it directly4: a vague question like "What do you want us to do about the wall?" forces the reviewer to guess what wall, what detail, and what conflict you're referring to— before they can begin formulating an answer.
Here's where format fails most often: the contractor wrote the bad RFI while standing next to the problem. The conflict felt obvious. But you can't read the label from inside the bottle. The reviewer is opening email number 47 that morning and knows nothing about Grid C-4. Write for them.
The Four Format Mistakes That Slow Down Your RFI Response
Most slow or unanswered RFIs share four format problems: a vague question, missing drawing references, no proposed solution, and no response deadline.
1. One question that contains multiple questions
If two unrelated issues are buried in a single RFI, the reviewer has to either answer both or set it aside to route it. Either way, you wait. DocumentCrunch5 and every major platform guide agree: one question per RFI. Two distinct issues need two RFIs. Separate submissions make tracking and routing significantly faster.
2. Vague or missing drawing references
"The wall at the second floor" is not a location. The reviewer should be able to open the drawing set and land on the exact spot before reading the question. The standard reference format is exact sheet, detail number, and gridline— something like "Drawing A3.2, Detail 5, Grid Line B."4 Nothing less qualifies as a reference.
3. No proposed solution
This is the single highest-leverage change you can make to how you write a construction rfi.
SubmittalLink research6 on 22 construction projects found that teams submitting RFIs early achieved median closure in 8 days, compared to 16 days for comparison groups— a 50% improvement.
When your RFI is complete the first time— question specific, references exact, solution proposed— there is no clarification loop before the clock starts. That's part of why early, complete submissions close faster.
Most contractors think proposing a solution is presumptuous. It isn't. When you propose a solution, you give the reviewer something to react to instead of something to solve from scratch. Most contractors submit the information they have; the RFI that gets answered delivers the insight the reviewer needs to act— a proposed solution, a clear deadline, a location reference they can confirm without a phone call.
4. Vague or missing deadline
"ASAP" is not a deadline. Tie the response needed date to a real field activity: "Response needed by Oct 13— concrete pour scheduled Oct 17." A calendar date with no context attached is easy to deprioritize. A date with a pour behind it is not.
When Not to Submit an RFI: Three Situations Where It Backfires
An RFI is the right tool when the answer isn't available in your contract documents. If the answer is already there— or the question is better resolved verbally— submitting an RFI slows the project and may trigger administrative charges.
Three situations where an RFI is the wrong move:
- The answer is in your documents. Check drawings, specifications, addenda, and prior submittals before submitting. Navigant Construction Forum research1 found that over 13% of RFIs on commercial projects were "not justifiable"— the answers already existed in the contract documents at time of submission. AIA G716 is explicit: submitting an RFI for information already in contract documents may result in administrative charges from the design team2.
- You need a quick verbal clarification. Pick up the phone. Then document the outcome in a letter or field directive request if it changes scope. RFIs are for formal questions that require formal answers and a documented record— not every field question needs that weight.
- The question involves routine trade practice. If the answer comes from your professional judgment on standard workmanship, use it. That's what you're licensed for.
The RFI is a permanent project record. Use it when you need a documented answer— not for every question that surfaces in the field.
Tracking Open RFIs and Where AI Tools Fit Into the Workflow
An untracked RFI is an invisible risk. When the schedule slips or a dispute surfaces, there is no record of when it was sent, when it was due, or who owned the response. Log every submission by number, date, responsible party, and expected response date.
At minimum, your RFI log should include:
- RFI number, subject line, submitted date
- Response deadline and assigned-to party
- Status (open / answered / closed)
A spreadsheet handles this on smaller projects. AIA G716 requires that RFIs be numbered, logged, and tracked through a document management system2. At scale, Procore and Autodesk Construction Cloud3 both handle this natively— with automated deadline tracking and routing built in.
On follow-up timing: SubmittalLink recommends6 following up at 75% of your expected response window. If you asked for 10 days, follow up on day 7 or 8, not day 11.
Two places where AI tools change what's possible in the RFI workflow:
- Pre-submission document check. Before writing an RFI, use an AI document review tool— Autodesk Construction Cloud's AI search, Procore's assistant, or Claude with the relevant spec sections pasted in— to check whether the answer already exists in the contract documents. This prevents unnecessary submissions, and the administrative charges that come with them. On large projects with complex spec sets, use a construction-specific platform with native document search rather than a general-purpose tool.
- Language review. Paste a draft RFI into an AI assistant and ask it to identify anything the reviewer would need to clarify before responding. Vague questions that felt clear while writing them often surface quickly under this test.
Autodesk Construction Cloud and Procore now build AI directly into RFI routing, deadline tracking, and response management— construction document control is where these tools are moving fastest. If your firm is working through how to integrate AI tools into project workflows, talk to someone about an AI implementation strategy before you buy the platform. Building that integration requires building an AI culture in your team first— the tools follow the practices. The format problem comes first.
Frequently Asked Questions About RFI Format in Construction
What is the standard RFI format in construction?
The industry-standard rfi format in construction follows AIA Document G716-20042, which requires eight fields: project identification, RFI number, submission date and response deadline, requester information, a single clear question, drawing and specification references, supporting documentation, and a proposed solution. Most digital platforms— Procore, Autodesk Construction Cloud— replicate these same fields.
How long should a construction RFI response take?
Under AIA A201 standard language7, the architect's review period typically shall not exceed seven calendar days from receipt. Navigant Construction Forum research1 shows the median response time on commercial projects is 9.7 days, with regional variation from 6.4 days (West US) to 9.7 days (Southeast US). Set your deadline tied to an actual field activity, not an arbitrary calendar date.
Should you always include a proposed solution in an RFI?
Yes— including a proposed solution is the single highest-leverage format improvement available. SubmittalLink research6 on 22 construction projects found that teams submitting RFIs early achieved median closure in 8 days compared to 16 days for comparison groups. When your RFI is complete the first time, there's no clarification loop before the clock starts— which is part of why early, complete submissions close faster.
What is the difference between an RFI and a submittal in construction?
An RFI resolves ambiguity or missing information in contract documents. A submittal confirms compliance— it's the contractor demonstrating that specified materials, shop drawings, or samples meet contract requirements. These are distinct document types used for different purposes, and the AIA governs both2.
What happens if an RFI goes unanswered?
Work cannot proceed on the affected scope without an authorized answer. Navigant Construction Forum research1 found that approximately 22% of RFIs on commercial projects never receive a formal response— and this is one of the strongest leading indicators of disputes arising later in the project. Document every follow-up attempt in writing.
The contractor who writes a clear RFI isn't doing more paperwork. They're thinking from the reviewer's seat. One question, exact drawing reference, proposed solution, deadline tied to field activity. That's what makes it possible for the reviewer to answer you without a follow-up call.
Get the format right the first time. The project doesn't have time for the re-send.
References
- Navigant Construction Forum via Construction Junkie, "The Cost of RFIs and Best Practices for Construction Professionals" (2015, citing 2013 Navigant study)— https://www.constructionjunkie.com/blog/2015/9/7/the-cost-of-rfis-and-best-practices-for-construction-professionals
- American Institute of Architects, "Summary: G716™–2004, Request for Information (RFI)"— https://help.aiacontracts.com/hc/en-us/articles/1500009444782-Summary-G716-2004-Request-for-Information-RFI
- Autodesk Construction Cloud, "RFI Templates for Construction" (2024)— https://construction.autodesk.com/resources/checklists/rfi-template/
- Young Architect, "RFI Meaning in Construction: The Complete Guide" (2024)— https://academy2.youngarchitect.com/what-is-an-rfi-construction/
- DocumentCrunch, "How to Write a Construction RFI That Gets Fast, Clear Answers" (2024)— https://www.documentcrunch.com/blog/how-to-write-an-rfi-construction
- SubmittalLink, "RFI Best Practices: A Guide for Construction Professionals" (2024)— https://www.submittallink.com/post/rfi-best-practices
- AIA PV Chapter, "The Protocols of Construction: The RFI" (2023)— https://aiapv.org/blog/id/176